THE MODEL FOR DETERMINING THE SEQUENCE OF WORKS AND OPERATIONS TO MANAGE THE TIMETABLE OF A CONSTRUCTION PROJECT

Authors

DOI:

https://doi.org/10.30837/2522-9818.2018.6.033

Keywords:

work sequence, hierarchical structure, level of operations, content and schedule management, construction project

Abstract

The subject matter is the issue of managing the content and schedule of a construction project. The goal of the article is to build structural models that determine the sequence and interrelation of works (and operations) of construction projects. The following tasks were solved: a model of the processes of project schedule management was built, a hierarchical structure of a construction project was developed taking into account the operation level, a precedence diagram was constructed for the level of works and operations. The following methods were used: the project approach, process modelling using IDEF0 diagrams, decomposition methods, the method of a precedence diagram.  The following results were obtained: the processes for managing the schedule of a project according to the PMBoK standard were analyzed, their features with were considered with reference to construction projects, as a result, a model of processes for managing construction project schedules presented in IDEF0 notation was built; the level of operations of the hierarchical structure of a construction project was considered; the factors of an enterprise that affect the list of operations were indicated; to compose operations, the decomposition method was used; the WBS-structure of the portfolio of construction projects, including three levels of hierarchy, was supplemented with the fourth level – operations; the examples of some elements of the specified sets of construction project operations were given; the method of precedence diagrams was chosen for determining the sequence of operations; a precedence diagram which indicates inputs and outputs was constructed for the level of the structure operations; a precedence diagram for the level of operations of the project structure was also built in the context of the task of the project documentation development. Conclusions. After establishing the sequence and logical relationship at the level of operations, taking into account the precedence diagram at the level of work, a model of the sequence of a group of operations, groups of work and then the entire project can be built. Taking into consideration the data on the duration of operations, this model will enable assessing the duration of the entire project. This will provide a reliable assessment of resources and the duration of operations. The result will be a project schedule with detailed project content.

Author Biographies

Анна Анатоліївна Дорохіна, State Enterprise "National Design & Research Institute of Aerospace Industries"

State Enterprise "National Design & Research Institute of Aerospace Industries", Lead Architect

Альона Юріївна Старостіна, O. M. Beketov National University of Urban Economy

PhD (Engineering Sciences), Associate Professor, O. M. Beketov National University of Urban Economy, Head of the Research Center at the Department of Project Management in Municipal Services and Building

Роман Володимирович Артюх, State Enterprise "National Design & Research Institute of Aerospace Industries"

PhD (Engineering Sciences), Associate Professor, State Enterprise "National Design & Research Institute of Aerospace Industries", Director

References

Kononenko, I., Lobach, E., Kolesnik, М. (2014), "The process of multi-criteria optimization of project content using PMBoK methodology", Bulletin of the National Technical University "KhPI", Seriya : Strategic management, portfolio management, software and projects, No. 2 (1045), P. 11–17.

Kononenko, I., Lobach, E., Kharazi, A. (2013), "Multicriteria optimization of the content of the project with the given priorities for the criteria", Open information and computer integrated technologies. Sat scientific of labor. National Aerospace University KhAI, No. 59, P. 6–13.

Hariga, М. (2016), "Integrated time–cost tradeoff and resources leveling problems with allowed activity splitting", International Transactions in Operational Research International Federation of Operational Research Societies Published by John Wiley & Sons Ltd, 9600 Garsington Road, Oxford OX4 2DQ, UK and 350 Main St, Malden, MA02148, USA, Р. 80–99.

Mejna, G., Niсo, K., Montoya, C., Sbnchez, M. A., Palacios, J. and Amodeo, L. (2016), "A Petri Net-based Framework for Realistic Project Management and Scheduling: An application in Animation and Videogames", Computers & Operations Research, Vol. 66, P. 190–198. DOI: https://doi.org/10.1016/j.cor.2015.08.011.

Li, F., Xu, Z. (2018), "A multi-agent system for distributed multi-project scheduling with two-stage decomposition", PLoS ONE, No. 13 (10). DOI: https://doi.org/10.1371/journal.pone.0205445.

Targiel, К., Maciej Nowak, М., Trzaskalik, T. (2018), "Scheduling non-critical activities using multicriteria approach", Central European Journal of Operations Research, No. 3, Р. 585–598. DOI: https://doi.org/10.1007/s10100-018-0542-y.

Creemers, S. (2015), "Minimizing the expected makespan of a project with stochastic activity durations under resource constraints", Journal of Scheduling, No. 18 (3), Р. 263–273. DOI: https://doi.org/10.1007/s10951-015-0421-5.

Kadikova, I., Kalinenko, B., Larina, S., Chumachenko, I. (2017), "Model of time management in the system of strategic project management", Innovative Technologies and Scientific Solutions for Industries, No. 2 (2), P. 29–37. DOI: https://doi.org/10.30837/2522-9818.2017.2.029.

Martynenko, O., Husieva, Yu., Chumachenko, I (2017), "The method of earned requirements for project monitoring", Innovative Technologies and Scientific Solutions for Industries, No. 1 (1), P. 58–63. DOI: https://doi.org/10.30837/2522-9818.2017.1.058.

A Guide to the Project Management Body of Knowledge (PMBoK guide), Sixth edition, USA : PMI Inc, 2017, 735 p.

Dorokhina, A., Starostina, A., Artyukh, R. (2018), "Conceptual model of construction project taking into account the interests of stakeholders", Advanced Information Systems, Vol. 2, No. 2, P. 17–22. DOI: http://doi.org/10.20998/2522-9052.2018.2.03.

Dorokhina, A., Starostina, A., Artyukh, R. Gopejenko V. (2018), "Developing the mechanism for systematizing the components of the content of the construction projects portfolio", Innovative Technologies and Scientific Solutions for Industries, No. 3 (5),

P. 17–25. DOI: http://doi.org/10.30837/2522-9818.2018.5.017.

Dorokhina, A., Starostina, A., Artyukh, R. (2018), "Structural models of the portfolio of investment and construction projects", Monograph Scientific-Practical conference "Mathematical modeling of processes in economics and management of projects and programs (MMP-2018), Kharkiv-Koblevo, P. 233–242.

Ulyanchenko, O., Tsigikal, P. (2010), "Project Management", Tutorial. Kharkiv National Agrarian university them V. V. Dokuchaev, P. 109–111.

Published

2018-12-17

How to Cite

Дорохіна, А. А., Старостіна, А. Ю., & Артюх, Р. В. (2018). THE MODEL FOR DETERMINING THE SEQUENCE OF WORKS AND OPERATIONS TO MANAGE THE TIMETABLE OF A CONSTRUCTION PROJECT. INNOVATIVE TECHNOLOGIES AND SCIENTIFIC SOLUTIONS FOR INDUSTRIES, (4 (6), 33–41. https://doi.org/10.30837/2522-9818.2018.6.033