Development of an integration­analytical method for the initiation of construction projects of industrial objects

Authors

DOI:

https://doi.org/10.15587/1729-4061.2018.142517

Keywords:

industrial object, life cycle of a project, specific resources, innovativeness

Abstract

We studied management processes of initiation of industrial projects. We considered the specific features of industrial objects construction projects that affect a structure of a project life cycle and a timetable for its financing. Technological parameters of a new construction object determine the specific features of project of construction of industrial objects. We determined that the modern toolkit for management of projects initiation processes is not able to provide a full pre­project analysis of alternative options for industrial objects construction projects. This justifies a need to create a comprehensive method for analysis of projects of construction of industrial objects at the initiation stage, which will take into consideration the specifics of projects and meet needs of initiators.

We developed the integration­analytical method for initiation of project of construction of industrial objects, which has a complex nature and takes into consideration the specifics of a life cycle of such projects. It has high level of innovation and a need for specific resources. The proposed method has a step­by­step procedure of execution, it provides an iterative process of analysis of projects of construction of industrial objects, and gives possibility to make an informed decision to refuse to implement a project, which does not perform all steps of the method. This reduces time required for the pre­project analysis of alternatives and the amount spent if implementation of projects of construction of industrial object is inexpedient.

The advantage of implementation of the integration­analytical method for initiation of projects of construction of industrial objects is to save time and resources necessary for management of initiation of projects of construction of industrial objects. We achieved this through integration and adaptation of existing analytical tools into a comprehensive method by elimination of cases of double consideration of similar indicators, and those that are not of key importance at this stage. But due to formation of the procedure for implementation of the method, which corresponds to a specific life cycle of projects of construction of industrial objects.

Author Biographies

Maria Sukhonos, O. M. Beketov National University of urban economy in Kharkiv Marshala Bazhanova str., 17, Kharkiv, Ukraine, 61002

Doctor of Technical Sciences, Professor

Department of project management in municipal services and building

Valentyn Shevetovsky, O. M. Beketov National University of urban economy in Kharkiv Marshala Bazhanova str., 17, Kharkiv, Ukraine, 61002

Postgraduate student

Department of project management in municipal services and building

Ievgenii Grytskov, O. M. Beketov National University of urban economy in Kharkiv Marshala Bazhanova str., 17, Kharkiv, Ukraine, 61002

PhD

Department of business economics, business adiminstrument and regional development

Alona Starostina, O. M. Beketov National University of urban economy in Kharkiv Marshala Bazhanova str., 17, Kharkiv, Ukraine, 61002

PhD

Department of project management in municipal services and building

References

  1. Leu, S.-S., Liu, С.-M. (2016). Using principal component analysis with a back-propagation neural network to predict industrial building construction duration. Journal of Marine Science and Technology, 24 (2), 82–90. doi: https://doi.org/10.6119/JMST-015-0325-2
  2. Alavipour, S. M. R., Arditi, D. (2018). Optimizing Financing Cost in Construction Projects with Fixed Project Duration. Journal of Construction Engineering and Management, 144 (4), 04018012. doi: https://doi.org/10.1061/(asce)co.1943-7862.0001451
  3. Babaev, V., Sukhonos, M., Starostina, A., Beletsky, I. (2016). Improving the processes of cost management in the construction and energy projects. Eastern-European Journal of Enterprise Technologies, 4 (3 (82)), 10–17. doi: https://doi.org/10.15587/1729-4061.2016.75515
  4. Hwang, B.-G., Shan, M., Phua, H., Chi, S. (2017). An Exploratory Analysis of Risks in Green Residential Building Construction Projects: The Case of Singapore. Sustainability, 9 (7), 1116. doi: https://doi.org/10.3390/su9071116
  5. Doerr, A., Pfnuer, A., Gloeck, C. (2017). Success factors and framework conditions for value-added partnerships in construction projects. An empirical analysis of corporate properties. Bauingenieur, 51–64.
  6. Eskerod, P., Ang, K., Andersen, E. S. (2018). Increasing project benefits by project opportunity exploitation. International Journal of Managing Projects in Business, 11 (1), 35–52. doi: https://doi.org/10.1108/ijmpb-07-2017-0089
  7. Pal, R., Wang, P., Liang, X. (2017). The critical factors in managing relationships in international engineering, procurement, and construction (IEPC) projects of Chinese organizations. International Journal of Project Management, 35 (7), 1225–1237. doi: https://doi.org/10.1016/j.ijproman.2017.05.010
  8. Nguyen, H. T., Hadikusumo, B. (2017). Impacts of human resource development on engineering, procurement, and construction project success. Built Environment Project and Asset Management, 7 (1), 73–85. doi: https://doi.org/10.1108/bepam-04-2016-0010
  9. Sukhonos, M., Shevetovsky, V., Starostina, A. (2017). Model of the life cycle of projects of industrial objects construction. Komunalne hospodarstvo mist. Seriya: tekhnichni nauky ta arkhitektura, 139, 10–14.
  10. Bеlopolskyi, M. G., Kuzmina, O. V. (2016). Substantiation of the strategy of sustainable development of industrial enterprises. The Bulletin of the Dnipropetrovsk University. Series: Management of Innovations, 6, 23–33. doi: https://doi.org/10.15421/191603
  11. Rusinko, M. I. (2014). Theoretical and methodological approaches to determining the potential of construction enterprises' innovative development. Ekonomika i orhanizatsiya upravlinnia, 3 (19) – 4 (20), 221–225.
  12. Malyar, N. N. (2014). Modeling bounded rational choice using fuzzy sets. Bulletin of Taras Shevchenko National University of Kyiv Series: Physics & Mathematics, 2, 161–165.

Downloads

Published

2018-09-18

How to Cite

Sukhonos, M., Shevetovsky, V., Grytskov, I., & Starostina, A. (2018). Development of an integration­analytical method for the initiation of construction projects of industrial objects. Eastern-European Journal of Enterprise Technologies, 5(3 (95), 45–58. https://doi.org/10.15587/1729-4061.2018.142517